How long do contractors have to file a lien?

  1. 30 days

  2. 4 months

  3. 2 months

  4. 6 months

The correct answer is: 6 months

Contractors have a specific timeframe in which they can file a lien to protect their rights regarding unpaid labor or materials supplied for a construction project. In Alabama, the law stipulates that a contractor must file a lien within six months after the last day of work performed or materials supplied on the project. This allows contractors ample time to ensure that they have fulfilled their obligations and to secure their financial interests in the project. Filing a lien within this six-month window not only protects the contractor but also serves as a legal claim against the property, which can compel the property owner to settle unpaid debts for the services rendered. Understanding this timeframe is crucial for contractors in maintaining their rights and ensuring they can effectively pursue payment for their work.