Study for the Alabama Contractors License Test. Prepare with quizzes featuring flashcards and multiple-choice questions, each supported by hints and explanations. Equip yourself for exam success!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following contract types distributes risk more evenly between parties?

  1. Fixed-price contracts

  2. Cost-plus contracts

  3. Time and material contracts

  4. Design-build contracts

The correct answer is: Design-build contracts

Design-build contracts are designed to streamline the construction process by combining both the design and construction phases under a single contract. This integrated approach allows for better communication and collaboration between the designer and the builder, which contributes to a more balanced distribution of risk between the parties involved. By having one entity responsible for both design and construction, there is a reduction in the potential for disputes that can arise when the responsibilities are separated, as is the case with traditional design-bid-build contracts. In a design-build contract, the contractor assumes greater responsibility for project delivery, which includes both meeting design specifications and staying within budgetary constraints. This shared responsibility helps mitigate risks associated with design errors and project delays, ensuring that both parties have a vested interest in the project's success. Ultimately, this results in a more even distribution of risk, as both the owner and the contractor work closely together to address challenges throughout the project lifecycle. In contrast, other contract types may lead to a more uneven distribution of risk, as they tend to place more risk on one party or the other. For example, fixed-price contracts can leave the contractor bearing the risk of cost overruns, while cost-plus contracts can result in the owner bearing more financial risk related to project costs. Time and material contracts